Appointed to replace a cracked second floor glazed unit at WTW Westgate in Redhill — Skyjack SJ45 boom MEWP access, controlled glass removal, replacement sealed unit, sealing, local making good and coordination with the WTW site management team.
Client
WTW
Sector
Commercial Offices / Facilities Management
Location
Westgate, 120-130 Station Road, Redhill, Surrey, RH1 1WS
Project Type
Second floor sealed glazed unit replacement (MEWP)
NZR was appointed to replace a cracked second floor glazed unit at WTW Westgate in Redhill. The project required high-level access using a Skyjack SJ45 boom MEWP, controlled glass removal, installation of a replacement sealed glazed unit, sealing, local making good, waste removal and coordination with the WTW site management team.
The damaged unit was located on the second floor of an occupied commercial office building. The works required safe MEWP access from the car park, controlled exclusion zones, careful glass handling, clear communication with site management and minimal disruption to staff, visitors and building operations.
NZR planned the works around the live office environment and car park access requirements. The team reviewed the RAMS, set up an exclusion zone, positioned the MEWP safely and accessed the second floor window externally. The cracked glazed unit was removed using controlled glazing methods before the replacement sealed unit was installed, packed, aligned, re-beaded, sealed and checked.
The cracked second floor glazed unit was replaced safely and professionally using controlled MEWP access. The works were completed with site coordination, RAMS, access control, sealing, local making good, waste removal and handover to site management.
High-level second floor glazed unit replaced safely under a controlled MEWP methodology — RAMS, exclusion zone, safe glass handling, sealing, making good and handover to site management.
A focused selection of project photography — site set-up and access control, the high-level glazing works themselves, and the finished replacement unit.
NZR van and Skyjack SJ45 boom MEWP set up in the car park with controlled exclusion zone and no-access barriers beneath the works area.




Skyjack SJ45 boom MEWP positioned against the second floor, with controlled removal of the cracked unit and installation of the replacement sealed glazed unit.




External and internal views of the completed second floor sealed glazed unit replacement.